Confirm the site Water Management Plan (WMP) is current, signed, and physically accessible at the plant
ContextThe WMP is the legal backbone of your Legionella control programme. Under HSE ACoP L8 (UK) and ASHRAE 188 (US), a documented, site-specific plan must exist before any inspection begins. Check the document date — if it hasn't been formally reviewed in the past 12 months, flag it for review before continuing. A WMP that doesn't reflect recent modifications to the cooling system (new heat exchangers, changed operating hours, replaced fill media) provides false confidence rather than genuine risk control. Keep a laminated summary at the plant for on-site reference, and ensure the full document version matches what's held centrally.